Handrail Installation – Kineton Primary School

Integrity FM recently completed a handrail installation project at a school in Birmingham. Our team was tasked with installing the new handrail system on an existing ramped footpath, improving safety and accessibility for all users.

Sequence of Works

Materials were procured and transported to site, from which our team commenced with the project. A safe working area was established before excavating pockets to either side of the footpath in preparation for receiving the handrail posts.

The traffic yellow handrail was then cut to the required lengths and fabricated on site, with all components assembled to the correct torque to ensure strength and durability. Once assembled, the handrails were carefully positioned and secured, ensuring they were fully vertical and correctly aligned along the ramp.

Following installation, the pockets were backfilled using rapid-set mass concrete, finished slightly below ground level. The surrounding areas were then reinstated with topsoil to maintain a neat and consistent appearance.

Outcome

The finished result is a robust, high-visibility handrail system that enhances safety and accessibility along the ramp. The project was completed efficiently and with minimal disruption, reflecting Integrity FM’s commitment to quality workmanship and client satisfaction.