Gym Refurbishment Works – Four Dwellings Primary Academy

Gym Refurbishment Works – Four Dwellings Primary Academy

A busy school gym needs to be practical, hard-wearing and easy to maintain. For this school gym refurbishment in Birmingham, Integrity FM was brought in to transform the existing walls through careful preparation, high-level decoration and hygienic cladding installation.

Our team arrived on site with all the necessary plant, tools and specialist access equipment required to complete the work safely and efficiently. Our team transported a MEWP and set it up within the gym, providing safe access to the high-level panelling.

Good preparation makes all the difference to the finished result, so the first stage focused on getting the existing surfaces into the best possible condition. Redundant screws, staples, adhesive putty and other unwanted fixings were removed before any remaining holes and imperfections were filled. Sections of loose panelling were securely fixed back into position, and the surfaces were thoroughly sanded to create a smooth and stable base for the new decorative finish.

Once the preparation was complete, a suitable primer was applied to the high-level panelling and allowed to dry thoroughly. This was followed by two coats of white paint, with the correct drying time allowed between applications. The new finish immediately helped to brighten the gym, giving the upper walls a clean, modern and refreshed appearance.

Attention then turned to the installation of the hygienic wall cladding. A dedicated workstation was established, allowing the sheets and trims to be prepared accurately while keeping the surrounding work area organised and safe. Starter trims and corner beads were installed first to create neat edges and a professional finish around corners and junctions. Adhesive was then applied to the hygienic cladding sheets before each sheet was carefully positioned and fitted to the wall. A pressure roller was used across the surface to promote full adhesion, remove trapped air and ensure an even, secure bond.

After the cladding had been installed, the protective film was removed and disposed of, revealing the clean finished surface beneath. The hygienic cladding provides a smooth, durable and easy-to-maintain finish that is well suited to the everyday demands of a busy school environment.

This Birmingham school gym refurbishment has created a cleaner, brighter space. By combining careful surface preparation with fresh decoration and robust hygienic cladding, the refurbishment has given the school gym a practical, professional finish designed to stand up to regular use.

You can find out more about our recent projects and the work we carry out here.

Unit Clearance – Osyth, Northampton

Project Overview

This project involved the large-scale removal and clearance of materials, equipment, and redundant stock from a redundant warehouse facility.

Our objective on behalf of the client, was to clear the site while maintaining operational safety standards, minimizing disruption, and ensuring all waste streams were managed responsibly safely and efficiently.

Given our tight deadline, a project schedule was developed to coordinate labour, vehicles, lifting equipment, and waste disposal requirements.

Prior to commencement, a full site assessment was completed to identify:

  • Access and egress routes
  • Manual handling risks
  • Weight and load considerations
  • Hazardous materials or restricted areas
  • Traffic management requirements within the warehouse

Our work included:

  • Removal of obsolete stock and palletised materials
  • Clearance of damaged and non-operational equipment
  • Segregation of recyclable and general waste materials
  • Loading and transportation of waste
  • Final sweep and clean-down of designated warehouse and office areas

Taking care of the environment:

Materials removed from the warehouse were separated where possible to maximise recycling and reduce landfill disposal.

Recyclable metals, wood, cardboard, and plastics were processed through approved waste management facilities.

Project Outcome

The warehouse clearance was completed successfully within the agreed timeframe.

The site was left clean, safe, and ready for its next operational phase.

The project demonstrated effective coordination, safe working practices, and efficient waste management throughout all stages of the removal works.

Through proper planning, experienced personnel, and adherence to health and safety standards, the works were completed with minimal disruption and a high standard of service delivery

 

Handrail Installation – Kineton Primary School

Handrail Installation – Kineton Primary School

Integrity FM recently completed a handrail installation project at a school in Birmingham. Our team was tasked with installing the new handrail system on an existing ramped footpath, improving safety and accessibility for all users.

Sequence of Works

Materials were procured and transported to site, from which our team commenced with the project. A safe working area was established before excavating pockets to either side of the footpath in preparation for receiving the handrail posts.

The traffic yellow handrail was then cut to the required lengths and fabricated on site, with all components assembled to the correct torque to ensure strength and durability. Once assembled, the handrails were carefully positioned and secured, ensuring they were fully vertical and correctly aligned along the ramp.

Following installation, the pockets were backfilled using rapid-set mass concrete, finished slightly below ground level. The surrounding areas were then reinstated with topsoil to maintain a neat and consistent appearance.

Outcome

The finished result is a robust, high-visibility handrail system that enhances safety and accessibility along the ramp. The project was completed efficiently and with minimal disruption, reflecting Integrity FM’s commitment to quality workmanship and client satisfaction.

We’re delighted to have had the opportunity to successfully deliver another high-standard installation and commend our staff on their professionalism and workmanship.

You can find out more about our recent projects and the work we carry out here.

Supply and Install Leak Diversion Kit – LKQ, Tamworth

Supply and Install Leak Diversion Kit – LKQ, Tamworth

This week, our team delivered the successful installation of a leak diversion kit for one of our valued clients at LKQ in Tamworth, ensuring full protection of critical machinery and maintaining uninterrupted operations.

Why Leak Diversion Kits Are a Smart, Effective Solution

Leak diversion kits offer a fast and highly reliable method for managing active leaks—especially in live environments where disruption must be kept to a minimum. Key advantages include:

Minimal Downtime: Systems can be installed swiftly without shutting down critical operations or access routes.

Cost-Effective Protection: Diverts water safely away from assets, equipment, and stock, preventing costly damage or operational impact.

Adaptable to Complex Spaces: Kits can be configured with hoses, bends, and fixings to suit challenging high-level or confined areas.

Temporary or Long-Term Use: Suitable as an immediate short-term measure or as part of a managed leak mitigation strategy.

You can find out more about our recent projects and the work we carry out here.

Vinyl Flooring Installation – Birmingham University, Centre of Defence

Vinyl Flooring Installation – Birmingham University, Centre of Defence

Integrity FM recently completed a vinyl flooring installation project at Birmingham University’s Centre of Defence, Birmingham.

Our team was tasked with replacing the existing carpet tile flooring in favour of vinyl flooring, allowing for ease of cleaning and revitalising the office and storage areas. Our team was responsible for the supply and installation of new vinyl sheet safety flooring across the two key areas.

Method of Works

Materials were procured and transported to site, from which our team commenced with the project. Works included…

  • Setting up a safe working area
  • Uplifting existing carpet tiles and removing all loose debris.
  • Applying a high-strength self-levelling compound to create a smooth, even surface.
  • Allowing sufficient drying time before returning to install the new flooring.
  • Measuring, cutting, and installing vinyl sheet safety flooring with precision.
  • Removing all waste materials and reinstating the area to its original condition.
  • Completing final checks and handing over the finished spaces to the client.

Outcome

The finished result is a professional, hard-wearing, and hygienic flooring solution that enhances both safety and appearance. The project was completed efficiently and with minimal disruption, reflecting Integrity FM’s commitment to quality craftsmanship and client satisfaction.

We’re delighted to have had the opportunity to successfully deliver another high-standard flooring installation and commend our staff on their professionalism and workmanship.

You can find out more about our recent projects and the work we carry out here.