Solihull College 2017 Deep Clean Of Kitchen Facilities

Solihull College 2017 Deep Clean Of Kitchen Facilities

Integrity Facilities Management carried out an extensive deep clean of the kitchen area at Solihull College.

High quality products were used to ensure the kitchen was left in immaculate condition.
Work surfaces, containment units, non-slip Flooring, Kitchen Extractor Hood (internal and external) were all cleaned to an excellent final result.

Project Details

Date Completed: March 2017
Client: Solihull College
Location: Blossomfield Road Campus

Roof Seal Solihull

Roof Seal Solihull

One of our clients reported a persistent problem with a leak inside their main office.

Integrity’s engineers primed the area and sealed the joints of existing felt cap and cove.
Once sealed, an area of address was completely covered with the solution to ensure of no further penetration.

Project Details

Date Completed: 17/06/17
Location: Cranmore Estate Solihull, West Midlands.

Resurfacing Works in Edgbaston

Resurfacing Works in Edgbaston

Resurfacing Works NHSBT – January 2017

After competitive tendering, Integrity Facilities Management were selected as the chosen provider to complete the re-surfacing of a critical, extremely busy road and service area at one of our client’s sites. Our road surfacing team undertook a site survey and produced a traffic management plan to enable the road to remain functional throughout and keeping disruption to a minimum.

Integrity FM undertakes resurfacing and reconstruction of roads, driveways, and footways by engineering with materials and processes that deliver long term value for money. It is essential that road surfaces are durable to sustain both heavy and high speed vehicles, treading across the surface day in and day out.

Our work on this project consisted of;

  • The raising of ironworks
  • Preparation of a variety of stone sub-base
  • Laying of asphalt products
  • Line markings

Our services are focused on providing best value, proficient management, and customer satisfaction. Our surfacing team are experienced in providing road resurfacing and footpath holding all relevant industry accreditations and exceeding the latest environmental and health and safety requirements.

At Integrity Facilities Management, Ltd, our main objective is to keep you and your working environment safe. We also provide both fast and efficient service!

Our detailed program of works ensures that road resurfacing is carried out according to client requirements and with minimum disruption to road users.

We provide a consultation service to ensure we provide the best value surfacing solution to every client, taking into consideration the type of road and purpose, location, volume and speed of traffic, aesthetic appearance, cost, maintenance requirements, product lifecycle, and the environment.

Project Details

Date Completed: January 2017
Client: NHS
Location: Edgbaston

NHS Birmingham Decking Project

NHS Birmingham Decking Project

In August 2016 and after a long tender process, Integrity Facilities Management were chosen by one of our NHS clients in Birmingham to carry out a whole re-decking of their communal area.

Our Client had a challenging situation in that they had timber decking installed on a flat roof adjacent to tree growth, causing a slip hazard.  As the decking was showing signs of decay, Integrity suggested installing a low maintenance composite decking system. This system was not only beneficial from a Life Cycle Costing benefit (as requires no subsequent treatment and is a durable material) but it also greatly reduces the risk of people slipping on it when wet.

Further, the Client was pleased to discover it is manufactured in several colour options to ensure it fits in with its surroundings. The staff at the building can now enjoy some outdoor space, allowing them to unwind during and after their hectic days at work.

Project Details

Date Completed: August 2016
Client: Decking Project
Location: Birmingham

Solihull College Refurbishment

Solihull College Life Sciences Refurbishment June – August 2016

Solihull College and University Centre works in partnership with local organisations such as the Heart of England and University Hospitals and Birmingham NHS to enhance the prospects of young adults in its further and higher education facility.

After a competitive tender process, and in line with a planned redesign and modernisation of their existing science block, Integrity Facilities Management were selected to complete a refurbishment of the adjoining classrooms, offices, meeting rooms, access points and amenity links.

After extensive planning and then implementation of deconstruction and reconstruction to the layout (inclusive of walls and movable walls, ceilings and flooring) Integrity Facilities Management paved the way for regenerating this academic environment inclusive of: redecoration, reconfiguration of heating and lighting (Invest to Save), networking and audio-visual systems. 

The completed works helped breathe new life and capacity into the existing building and enabled to learners to study and learn inside the newly bright, clean and modern facility.

Are you looking for a refurbishment that supports your business to progress and develop? (link into ‘contact us’)

  • Deconstruction of partition walls
  • Designed and erected stud walling to optimise space utilisation
  • Renewed surface finishes to all walled areas
  • Installed an ‘Invest to Save’ lighting system, whilst enhancing lighting levels
  • Removed and refitted audio visual equipment
  • Installed suspended ceiling systems
  • Supplied and fitted a fire compliant metal door system
  • Reconfigured heating system
  • Installed new networking provision
  • Redecoration of all areas
  • Supplied and fitted moveable wall systems
  • Renewed floor areas and carpet tiles to match existing
  • Designed and laid Altro flooring

Project Details

Date Completed: August 2016
Client: Solihull College
Location: Solihull, West Midlands
Value: (8 weeks on site)